NEW QUESTION # 50
Which of the following will always describe the critical path? The path with
- A. The longest duration through the network.
- B. The shortest duration and negative float.
- C. Zero float.
- D. Negative float.
Answer: C
NEW QUESTION # 51
What is the workweek period for this project?
- A. Monday through Saturday
- B. Sunday through Friday
- C. Monday through Friday
- D. Sunday through Saturday
Answer: D
NEW QUESTION # 52
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
- A. Is a milestone.
- B. Was completed in the past.
- C. It is on the critical path.
- D. Has yet to be completed.
Answer: D
NEW QUESTION # 53
Determine the driving activity for Activity 10001.
- A. Activity 10002.
- B. There is no driving activity for Activity 10001 in the backward pass.
- C. Activity 9005.
- D. Activity 11001.
Answer: A
NEW QUESTION # 54
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 18 work days
- B. 7 work days
- C. 15 workdays
- D. 8 work days
Answer: D
NEW QUESTION # 55
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 20 months.
- B. 19 months.
- C. 21 months.
- D. 22 months.
Answer: A
NEW QUESTION # 56
At a minimum, periodic reporting must be done at what interval?
- A. As requested by the project manager.
- B. Monthly.
- C. As specified in the contract documents.
- D. As requested by the owner.
Answer: C
NEW QUESTION # 57
Why does activity 11001 not show successor activities?
- A. It is the penultimate work required for the project
- B. The early finish and late finish are circular
- C. It is the final activity for the required work for the project
- D. The scheduler forgot to add the successor activities
Answer: C
NEW QUESTION # 58
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
- A. 20 lifts
- B. 5 lifts
- C. 80 lifts
- D. 50 lifts
Answer: D
NEW QUESTION # 59
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
- A. Time impact analysis
- B. Historical production rates
- C. Black-Scholes model
- D. The Eichleay formula
Answer: B
NEW QUESTION # 60
What does the heavy, vertical line at "X" represent?
- A. Delay fault line.
- B. International Date Line.
- C. The status or data date.
- D. Change-over limits.
Answer: C
NEW QUESTION # 61
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
- A. Expedite printing by 5 days.
- B. Delay product release by 5 days.
- C. Delay manufacturing by 5 days.
- D. Expedite packaging by 5 days.
Answer: B
NEW QUESTION # 62
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 4001, 5001 and 6001.
- B. 2004.
- C. 2003 and 7001.
- D. 4001 and 5001.
Answer: D
NEW QUESTION # 63
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Periodic Windows.
- B. Gantt Chart.
- C. Time Impact.
- D. Collapsed As-Built.
Answer: B
NEW QUESTION # 64
Determine the correct formula and date for the late finish for Activity 2001.
- A. LS.2002 - 1 day -> 08-28-01.
- B. LS.2002 + 1 day -> 08-30-01.
- C. LF.2001 - 1 day -> 08-28-01.
- D. LS.2002- 1 day-> 08-29-01.
Answer: A
NEW QUESTION # 65
Project schedules help control all of the following EXCEPT for_____________________.
- A. Cost
- B. Quality
- C. Time
- D. Resources
Answer: B
NEW QUESTION # 66
Determine the correct formula and date for the late start for Activity 9001.
- A. LF.9001 Dur.9001 -> 11-20-02.
- B. There is insufficient data provided to calculate the answer.
- C. LS.6001 Dur.6001 -> 11-20-02.
- D. The early finish is required in order to determine the answer.
Answer: A
NEW QUESTION # 67
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 10 days.
- B. 15 days.
- C. 0 days.
- D. 5 days.
Answer: C
NEW QUESTION # 68
What is the free float for Activity F?
- A. 0months.
- B. 2month.
- C. 1months.
- D. 3 months.
Answer: A
NEW QUESTION # 69
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
- A. 03-11-04
- B. 02-19-04
- C. 03-21-04
- D. 03-20-04
Answer: A
NEW QUESTION # 70
......