NEW QUESTION 51
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

  • A. 10 days.
  • B. 0 days.
  • C. 5 days.
  • D. 15 days.

Answer: B

 

NEW QUESTION 52
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

  • A. Estimating remaining durations of activities.
  • B. The correct recording of actual start dates.
  • C. Entering the time impacts of delays and change orders.
  • D. Making "downstream" logic revisions as required.

Answer: D

 

NEW QUESTION 53
Constraints control events or activities that __________________.

  • A. May be over-ridden by activity logic.
  • B. Affect only the backward pass.
  • C. Affect only the forward pass.
  • D. Are not based on project relationships.

Answer: A

 

NEW QUESTION 54
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • C. The activities run concurrently.
  • D. The activities occur in series with a 15-day lag.

Answer: D

 

NEW QUESTION 55
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

  • A. Negative float.
  • B. Total float.
  • C. Interfering float.
  • D. Free float.

Answer: B

 

NEW QUESTION 56
What does the heavy, vertical line at "X" represent?

  • A. International Date Line.
  • B. Delay fault line.
  • C. The status or data date.
  • D. Change-over limits.

Answer: C

 

NEW QUESTION 57
Identify the minimum project duration.

  • A. 20 months.
  • B. 21 months.
  • C. 16 months.
  • D. 19 months.

Answer: A

 

NEW QUESTION 58
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. 1.
  • B. 2.
  • C. 3.
  • D. Does not change.

Answer: D

 

NEW QUESTION 59
What is the workweek period for this project?

  • A. Sunday through Saturday
  • B. Sunday through Friday
  • C. Monday through Saturday
  • D. Monday through Friday

Answer: A

 

NEW QUESTION 60
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

  • A. Consideration of all stakeholders.
  • B. Value engineering.
  • C. Project variables.
  • D. Interest rate of owner's construction bonds.

Answer: D

 

NEW QUESTION 61
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. There is no such thing.
  • B. It is calculated using the original logic.
  • C. An out-of-sequence activity cannot resume until all predecessors are finished.
  • D. It is calculated using logic reflecting out-of-sequence progress.

Answer: B

 

NEW QUESTION 62
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

  • A. Compensable delay
  • B. Excusable delay
  • C. Non-compensable delay
  • D. Non-excusable delay

Answer: C

 

NEW QUESTION 63
All the following describe the critical path of a schedule EXCEPT:

  • A. Determined by network logic and is the chain of activities that controls the overall project completion time.
  • B. Frequently defined as the shortest path through the schedule.
  • C. Changed by redefining the network logic or changing activity durations or both.
  • D. The series of activities having the least amount of total float.

Answer: B

 

NEW QUESTION 64
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 10 days.
  • B. 5 days.
  • C. 0 days.
  • D. 15 days.

Answer: B

 

NEW QUESTION 65
Each of the following accurately describes total float in a schedule EXCEPT:

  • A. Can be positive or negative.
  • B. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  • C. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
  • D. The amount of time an activity can be delayed without delaying the overall project completion time.

Answer: B

 

NEW QUESTION 66
What is the actual duration as of the status date or data date of Activity B?

  • A. 7.
  • B. 3.
  • C. 0.
  • D. 4.

Answer: B

 

NEW QUESTION 67
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 + 1 day -> 11-29-03.
  • B. LS.10002^ Lag.7 + i day -> 11-20-03.
  • C. LS.10002 - Lag.7 - l day -> 11-20-03.
  • D. LS.10002 - 1 day -> 11-27-03.

Answer: B

 

NEW QUESTION 68
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Actual finish of activities.
  • B. Percent complete.
  • C. Original duration of activities.
  • D. Remaining duration of activities.

Answer: D

 

NEW QUESTION 69
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inappropriate definition of work breakdown structure
  • B. Inadequate definition of scope at the estimate (budget) stage
  • C. lack of detailed planning for operational start-up
  • D. Insufficient planning for change management

Answer: B

 

NEW QUESTION 70
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

  • A. Testing, Manufacturing and Packaging.
  • B. Printing the Manual.
  • C. Packaging only.
  • D. Drafting and Proofing the Manual.

Answer: A

 

NEW QUESTION 71
How could the structural steel drawing delay have been prevented?

  • A. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
  • B. Switch to post-tensioned concrete construction.
  • C. Add a time buffer at the end of structural steel activities.
  • D. Allow adequate time for review and resubmittal in the baseline schedule.

Answer: C

 

NEW QUESTION 72
Which activity is drawn in the incorrect position?

  • A. Activity D.
  • B. Activity E.
  • C. Activity C.
  • D. Activity G.

Answer: A

 

NEW QUESTION 73
What owner action could have mitigated the late completion of the project?

  • A. Use a procurement agent to monitor and expedite equipment deliveries.
  • B. Prepare better structural steel drawings.
  • C. Self-perform more of the work.
  • D. Hire a more senior project manager.

Answer: A

 

NEW QUESTION 74
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Estimate at completion (EAC)
  • B. Budget at completion (BAC)
  • C. Budgeted cost of work scheduled (BCWS)
  • D. Budgeted cost of work performed (BCWP)

Answer: B

 

NEW QUESTION 75
......