Still upset about the coming exam? Replace worry with rehearsal: ExamCost's PRINCE2 Agile Practitioner Project Management material — 50 practice questions for the PRINCE2-Agile-Practitioner exam — turns anxiety into preparation in 2026.
PRINCE2 PRINCE2-Agile-Practitioner Exam Overview:
| Certification Vendor: | AXELOS / PeopleCert |
|---|---|
| Exam Name: | PRINCE2 Agile Practitioner Project Management Exam |
| Exam Number: | PRINCE2-Agile-Practitioner |
| Available Languages: | Portuguese (Brazil), French, Dutch, English, German, Spanish, Polish, Italian, Japanese, Chinese |
| Related Certifications: | PRINCE2 Agile Foundation PRINCE2 Practitioner |
| Real Exam Qty: | 50 |
| Passing Score: | 60% (30/50) |
| Exam Duration: | 150 minutes |
| Exam Price: | USD $400 - $780 |
| Exam Format: | Objective testing, Multiple choice, Scenario-based, Open book |
| Certificate Validity Period: | 3 years |
| Recommended Training: | PRINCE2 Agile Accredited Training Providers |
| Exam Registration: | PRINCE2 Official Site PeopleCert Official Registration |
| Sample Questions: | ![]() |
| Exam Way: | Online remote proctored or onsite; open book (official PRINCE2 Agile guide only) |
| Pre Condition: | Hold PRINCE2 Agile Foundation certification; or PRINCE2 Foundation / Practitioner + Agile qualifications |
| Official Syllabus URL: | https://www.peoplecert.org/browse-certifications/project-programme-and-portfolio-management/PRINCE2-Agile-28/prince2-agile-practitioner-4076 |
PRINCE2 PRINCE2-Agile-Practitioner Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: PRINCE2 Processes in Agile | - Closing a project - Directing a project - Controlling a stage - Managing stage boundaries - Initiating a project - Managing product delivery - Starting up a project |
| Topic 2: PRINCE2 Themes in Agile Context | - Plans - Risk - Business case - Progress - Organization - Change - Quality |
| Topic 3: Roles and Responsibilities | - Adapting PRINCE2 roles for agile teams - Agile-specific roles and integration |
| Topic 4: Management Products | - Agile artifacts and PRINCE2 alignment - Tailoring documents and artifacts |
| Topic 5: Introduction to PRINCE2 Agile | - Combining PRINCE2 and Agile
|
| Topic 6: The Agile Hexagon | - Fixing and flexing: scope, quality, time, cost, risk, benefits - Setting tolerances and adaptability |
| Topic 7: Practical Application and Tailoring | - Applying PRINCE2 Agile in different contexts - Scaling and adapting for different project sizes |
| Topic 8: PRINCE2 Agile Principles | - Tailoring PRINCE2 principles for agile environments - Agile-focused principles and behaviors |
PRINCE2 Agile Practitioner Project Management Exam FAQ — Clear and Current
Hold PRINCE2 Agile Foundation certification; or PRINCE2 Foundation / Practitioner + Agile qualifications Vendors revise eligibility rules periodically, so confirm the current requirements on the official page (official PRINCE2-Agile-Practitioner exam page) before registering.
Delivery is instant — an automatic email within a minute of payment, unlimited devices, and 7*24 online service (replies within two hours) if anything's missing after 2 hours; check spam first. If you fail the corresponding PRINCE2-Agile-Practitioner exam within 60 days of purchase, we refund all the cost you paid: send a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam, processed within 7 days. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. Alternatively, exchange for two equal-value products free.
150 minutes for 50 questions. Train the pace in advance: timed practice sessions turn the exam clock from a threat into a habit.
Yes:
Official courses build the base; the 50 practice questions for the PRINCE2 Agile Practitioner Project Management — every answer expert-verified — build the readiness.
The PRINCE2 Agile Practitioner Project Management blueprint spans 8 domains — including Practical Application and Tailoring, PRINCE2 Processes in Agile, PRINCE2 Agile Principles. Study in proportion to the weightings; the complete outline above details every subtopic.
Yes — free demo downloads let you tell whether the PRINCE2 Agile Practitioner Project Management material suits you before purchasing. Purchases include 365 days of free updates, each new version emailed immediately; renew afterward at 50% off.
Through the vendor's official registration channels:
The PRINCE2 Agile Practitioner Project Management is delivered Online remote proctored or onsite; open book (official PRINCE2 Agile guide only) — choose the arrangement that fits you when booking.
USD $400 - $780 per attempt, 60% (30/50) to pass. Retakes bill again at full price — prepare thoroughly with the 50 practice questions for the PRINCE2-Agile-Practitioner exam at ExamCost first.
The PRINCE2 Agile Practitioner Project Management is PRINCE2's certification exam for PRINCE2 Agile Practitioner, at the Practitioner level. These certifications are valued precisely because they're demanding — passing one validates real capability. Related credentials include PRINCE2 Agile Foundation, PRINCE2 Practitioner.
PRINCE2 Agile Practitioner Project Management Sample Questions:
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
When contributing to the development of the communication management approach, the Marketing Team felt that the only applicable agile technique to be included in the approach was the use of daily stand-ups.
Which reason BEST explains whether this is a suitable entry for 'tools and techniques' in the communication management approach?
- A. It is unsuitable because the daily stand-up is NOT a communication tool or technique.
- B. It is suitable because the marketing products are already rich in communication.
- C. It is suitable because the marketing products do NOT suit the use of other agile techniques.
- D. It is unsuitable because the other teams will need a means to be updated on progress and feedback.
Correct Answer: D 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager has agreed with the Website team manager delivering the Social Media work package that the team should try using the Kanban method along with their existing Scrum approach to improve delivery.
The team is now going to use a Kanban board as part of their information radiator.
Which explains the additional benefit of combining these two agile approaches during the 'managing product delivery' process?
- A. By using Kanban, collaborative working is enabled between members of the Website Team delivering the social media.
- B. Using Kanban limits the amount of scope change on the project and therefore increases velocity.
- C. A Kanban board makes the status of the Social Media work package visible to the delivery team.
- D. Using Kanban limits the amount of work being carried out by the team, with the aim of improving delivery during the sprint.
Correct Answer: C 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox.
One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox.
Which BEST explains how this approach manages change?
- A. It is a poor approach because some of the website pages should be moved to the next timebox.
- B. It is a poor approach because exploration is a behaviour that requires a creative environment to enable change.
- C. It is a good approach because changes at the high level for a timebox will NOT affect the baseline.
- D. It is a good approach because changes to the website information should be based on feedback.
Correct Answer: D 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Website team manager has identified the need for a supplier representative to work on the social media website.
Who can fulfil this need according to the 'defined roles and responsibilities' principle?
- A. The project manager who has a good overview of the entire project and the social media requirements.
- B. The senior supplier who has technical knowledge of the website and how it should be delivered.
- C. The team manager who is leading the delivery of the social media website.
- D. The senior user who is able to represent those who understand how social media channels are to be delivered.
Correct Answer: B 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
- A. The health and safety training should be left out if it cannot be delivered before the football tournament.
- B. The training must be delivered so that the volunteers understand the health and safety requirements.
- C. staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training Team have developed the following user story:
'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target? - D. the event is carried out safely and professionally;
- E. The health and safety training must be delivered before the planned football tournament takes place.
- F. The volunteers will take time to understand the training before they can apply it safely.
Correct Answer: C 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Viewing page 1 out of 10 pages.
Viewing questions 1-5 out of 50 questions.