How to choose the three versions of Construction-Manager exam dumps
Many candidates find that our CMAA Construction-Manager exam dumps have PDF version, SOFT (PC Test Engine) and APP (Online Test Engine). Even after they try the free demo download, they are still not sure how to choose. If you are purchasing for your company I will advise you purchase all the three versions of Construction-Manager exam dumps. Each candidate has their own study methods and habits. If you are purchasing for yourself, you can pick one version as you like.
PDF version ---- this version of Construction-Manager exam dumps is convenient for printing out, writing and studying on the paper. If you just want to know the exam collection materials or real Construction-Manager exam questions, this version is useful for you.
SOFT (PC Test Engine) ---- this version of Construction-Manager exam dumps is available for being installed on the Windows operating system and running on the Java environment. You can not only know the Construction-Manager exam collections materials or real exam questions but also test your own exam simulation test scores. It boosts your confidence while real exam.
APP (Online Test Engine) ---- this version of Construction-Manager exam dumps is the update of Software version. Online Test Engine supports Windows / Mac / Android / iOS, etc. It can be installed in all electronics. It contains all uses of Software version. After downloading it also support offline operate. You can study wherever you want.
Products First, Service Formost!
ExamCost not only provide best CMAA Construction-Manager exam dumps but also best golden customer service. Our customer service staff is working 7*24 on-line (even official holiday). Whenever you contact us or email us about Construction-Manager exam dumps we will reply you in two hours. Whenever the payment is completed we will send you the valid Construction-Manager exam dumps link and password in half an hour. After you passed Certified Construction Manager (CCM) we will give exam voucher for another exam dumps discount if you want.
We guarantee all candidates can pass exam 100% for sure under the help of Construction-Manager exam dumps. Don't hesitate, just come and try!
Instant Download Construction-Manager Exam Braindumps: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
The Construction-Manager test cost is high, our exam dumps will help you pass exam once.
As we all know the Construction-Manager test cost is very expensive. The average passing rate for CMAA Construction-Manager exam is 15% or so every year. In fact most exam cost for IT certifications is from $200 to $4000 which is not cheap. If you fail exam you should pay test cost twice or more. All ExamCost exam dumps cost is from $28 to $80. Our exam dumps can guarantee you pass exam 100% for sure at first shot. Why don't you consider purchasing our exam dumps? Especially for Certified Construction Manager (CCM)! If you purchase our Construction-Manager exam dumps we guarantee you pass exam just once so that you will not pay double test cost and waste double time & spirit. Why don't you?
ExamCost is the best provider with high pass rate in Construction-Manager exam dumps
Why do you choose our Construction-Manager exam dumps? Because our exam dumps material is really strong and powerful. Sometimes candidates find all Construction-Manager exam questions on the real test are included by our Construction-Manager exam collection. Normally we can make sure our Construction-Manager exam dumps contain 75%-80% exam questions & answers of the Certified Construction Manager (CCM) real test. So we say if you pay close attention on our exam dumps you will pass exam for sure. Part of excellent candidates will get a wonderful passing score. ExamCost is the best provider with nearly 100% pass rate in Construction-Manager (Certified Construction Manager (CCM)) exam dumps and will be your best choice.
CMAA Certified Construction Manager (CCM) Sample Questions:
1. An inexperienced client on a design-bid-build project states that they do not want the designer to assist in the review of submittals, respond to Requests for Information (RFIs). or conduct any site inspections during the construction phase. How should the CM respond to the client's request?
A) Review the Project Management Plan (PMP) and proceed accordingly.
B) Agree with the client that this will save the project from unnecessary costs and report that the design documents should be error-free.
C) Ignore the client and continue coordinating with the design professional to provide these necessary services as part of their contract.
D) Review the Project Procedures Manual (PPM) and then discuss with the client why their approach may add more risk to the project.
2. The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
A) CxA
B) Regulatory agencies
C) Designer
D) CM
3. An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?
A) The owner should charge the contractor daily liquidated damages.
B) The owner should plan for delayed completion.
C) The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.
D) Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.
4. A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?
A) 286
B) 700
C) 0.0014
D) 150
5. A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
A) On schedule, pay application accurately reflects percentage complete.
B) On schedule, pay application exceeds percentage complete.
C) Behind schedule, pay application accurately reflects percentage complete.
D) Behind schedule, pay application exceeds percentage complete.
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: D | Question # 3 Answer: D | Question # 4 Answer: B | Question # 5 Answer: C |